Summary
The first building permit for a metro station in Israel has been issued, for the underground structure of a station in Ariel Sharon Park on line M3, while the cost estimate has risen from about NIS 150 billion in the law (2021 prices) to NIS 177 billion and the first phase has slipped from 2030 to 2037, Bizportal reports. For buyers abroad this is a long-term factor around future station areas rather than a near-term change. FindBayit helps buyers abroad act on changes like this with a licensed Israeli broker and a U.S. CPA in one team.
Key takeaways
- About 20 of the 109 planned stations will be in Tel Aviv, mainly on Ibn Gabirol, in the old center near the Carmel Market and Magen David Square, and at Savidor; NTA runs about 30 work sites in Gush Dan, expected to approach 70 next year.
- The budget set in law is about NIS 150 billion (2021 prices) and the updated estimate is NIS 177 billion; the State Comptroller warns of about NIS 12 billion more, and senior NTA and Finance Ministry officials speak of about NIS 200 billion.
- The first phase, planned to operate in 2030, has been postponed to 2037 and the second phase to 2042; the State Comptroller writes that even the new dates are not well enough grounded.
- FindBayit matches buyers abroad with real, verified properties and guides them until closing at the best price and terms available, with a licensed Israeli broker and a U.S. CPA in one team.
Bizportal reports that the first permit to build a metro station in Israel was recently issued, for the underground structure of a station at Ariel Sharon Park on line M3, and that preparation work is advancing on all three lines. Work is now moving into central Tel Aviv, where about 20 of the 109 stations will be built, mainly along Ibn Gabirol, in the old center near the Carmel Market and Magen David Square, and at the Savidor station, where preparation for line M1 began about a year ago. NTA, the company building the system, runs about 30 work sites in Gush Dan, and the number is expected to approach 70 next year. The permit for the Ariel Sharon Park station estimates about 25 months of work for the underground structure alone.
On cost, the budget set in law is about NIS 150 billion in 2021 prices. The updated estimate is NIS 177 billion, the State Comptroller warns of a further overrun of about NIS 12 billion, and senior NTA and Finance Ministry officials speak of about NIS 200 billion, which the article calculates as about NIS 1.3 billion per kilometer. Funding comes from the state budget, a special betterment levy on properties near the stations, and congestion fees on private vehicles entering Gush Dan. Deputy Accountant General Oshrat David Decker said the congestion fees are not yet being collected and collection is expected to begin in about two years.
The system includes three lines, about 150 kilometers of tunnels and 109 stations, passing through 24 local authorities where more than three million people live. The first phase, planned to operate in 2030, was postponed to 2037, and the second phase to 2042; the State Comptroller writes that the new dates are also not well enough grounded. The article notes that Tel Aviv's master plan TA/5500 adds at least about 100,000 apartments and 6 million square meters of employment space, most of it around metro stations.
The Comptroller also points to a shortage of thousands of engineers, which may reach 8,000, and the project will need about 16,000 foreign workers at its peak around 2030. NTA's CEO, Itamar Ben Meir, said the company will issue 11 tenders worth about NIS 65 billion in the next year and a half. The Knesset Interior Committee approved regulations that set aside at least NIS 0.5 billion to help businesses near the work sites, including a 60% refund of municipal property tax (arnona) on up to 120 square meters. The article's author also argues that the project at this scale and schedule may not be feasible; that is the writer's opinion and not an official finding.
What this means for buyers abroad: Buyers abroad looking at Tel Aviv-area property near a planned station should treat metro access as a long-term prospect: the first phase is now planned for 2037, and the Comptroller says the dates are not well grounded. Construction at station sites can also affect nearby streets for years. A special betterment levy on properties near stations is mentioned as one source of funding, so it is worth watching how it is defined before assuming the cost of a specific property.
Source: Bizportal, 14 November 2026
Why buyers abroad choose FindBayit
Real, verified properties. We find real homes across the Israeli market, working directly with developers and in cooperation with other agents, and we check them before we show them to you.
Matched to you. We start with your situation, budget and preferences, then shortlist, and show homes by video tour so you can decide from anywhere.
Guidance until you close. A comparable-sales price check, negotiation support and coordination of everyone involved in your purchase, all aimed at the best price and terms for the property you want.
A licensed broker and a US CPA, in one team. Pinny Rozen, licensed Israeli real estate broker (license 3161674), and Arik Rozen, CPA, MBA, who guides the U.S. tax side of your purchase.
On your side only. We represent buyers only. Our fee is explained in writing before we show any property, and we take no referral fees from the lawyers, engineers or advisers we recommend.